Commercial showroom upgrade completed by the Needhamair in-house team
With a quick turn around and only a 5 day window on site, our install team removed & decommissioned 8 x commercial evaporative coolers and replaced them with 6 x 25kW reverse cycle ducted air conditioning units to 36 outlets and 12 return air grilles.
With a building height of 7m, all outdoor units were carefully craned onto the roof and existing units craned off then being removed from site. Internally the installation of indoor fan coils, sheet metal, flexible ductwork, drains and refrigerant pipework were performed using 4 x scissor lifts allowing the team of 8 installers to work at the heights required efficiently and safely.
A huge effort by the team to coordinate the logistics, crane lifts, scissor lifts, custom ductwork, electrical and commissioning — delivering a modern, energy-efficient climate control solution ready for all seasons in a tight 3-week window from enquiry to completion.