New extension and renovation works completed for Dapto Veterinary Clinic — final inspection ✅️
A fully customised design and construct solution, from architectural and engineering through to construction, delivered while the clinic stayed open and operational the whole way through.
We planned for fourteen days of shutdown. We delivered it in eleven, staged across the twenty eight week program to keep disruption to a minimum.
The scope included a full carpark upgrade, three additional consult rooms, a new laboratory and pharmacy, an additional operating theatre, new cage room facilities, a new accessible ramp, and a full exterior and interior upgrade including reception, facade and reroof. Also delivered: new staff room, staff bathroom facilities, laundry and kitchenette.
Big thank you to our subbies, suppliers and the whole team for getting us there.