Shenstone School Project, Belvedere - Apex Contractors Ltd

Shenstone School Project, Belvedere - Apex Contractors Ltd The Apex Team would like to share news & updates of the new SEN School we are building - Shenstone.

A few weeks ago, we were delighted to welcome Men in Sheds, a group organised by Age UK BEXLEY to our Shenstone School p...
30/06/2025

A few weeks ago, we were delighted to welcome Men in Sheds, a group organised by Age UK BEXLEY to our Shenstone School project.

Men in Sheds brings together retired men with backgrounds in hands-on trades. They meet regularly to build timber-based projects which often support the local community.

We approached Men in Sheds and their lead Emily Willey, last summer to explore ways we could collaborate on a project for Shenstone School's new garden. Since then, our project team have been setting aside timber offcuts in preparation for the collaboration. Last week, Men in Sheds confirmed they have enough material to create picnic benches, standard benches, and raised planters - designed for wheelchair accessibility, more than we originally hoped to achieve.

The group will also visit the school when it opens in September to build bird boxes alongside the students - a great way to get the pupils involved whilst teaching practical skills and learning about sustainability.

It was a real pleasure to have Men in Sheds join us, not only are they excited to start the project, they enjoyed being back on site, reminiscing about their days on the tools, and hearing how our team about how the construction process has evolved.

It is great to see this partnership finally come to life. This is a fantastic example of how social value and the circular economy can come together to enrich the lives of others.

Photos of the end result to come soon!

Social Value Lead, Sasha Silk | Project Team, Nathan C***s, Darran Richardson, Darren Lillis | Head of Social Value, Steph Harris

Client: London Borough of Bexley, TKAT ACE & Shenstone School, Lori Ann Mackey

Progress Update: Shenstone Belvedere Construction SiteHere’s a look at what we’ve been up to as we kick off the new year...
27/01/2025

Progress Update: Shenstone Belvedere Construction Site

Here’s a look at what we’ve been up to as we kick off the new year. It’s all systems go on site, with significant progress across all four buildings.

• Building 1 (Teaching Block): The external cladding has been completed and scaffolding have been removed.
• Building 2 (Art & Food Tech): Floor screed and roof joint installations have been successfully completed.
• Building 3 (Sports Hall & Canteen): Floor screed is done, along with the first fix of mechanical and electrical (M&E) works.
• Building 4 (New Teaching Building): First-fix partitions and floor screed are now complete.

Looking ahead, here’s what’s next:

• Building 1: Installation of door sets and grid ceilings.
• Building 2: Roof works, windows, and external doors.
• Building 3: External cladding, fascia works, windows, and external doors.
• Building 4: Facing brickwork.

With all buildings moving forward towards internal fitout stages we will continue to keep you updated as the project progresses.
Should you have any questions about the site, please do not hesitate to reach out.

We would like to inform you of our Christmas hours:Tuesday 24th December - CLOSEDWednesday 25th December - CLOSEDThursda...
11/12/2024

We would like to inform you of our Christmas hours:

Tuesday 24th December - CLOSED
Wednesday 25th December - CLOSED
Thursday 26th December - CLOSED
Saturday 27th December - CLOSED
Monday 30th December - CLOSED
Tuesday 31st December - CLOSED
Wednesday 1st January - CLOSED
Thursday 2nd January - OPEN - BACK TO BUSINESS AS USUAL

Should there be an emergency on site please contact Darran Richardson on 07716 224579 or Nathan C***s on 07585 900431

We would like to wish you and your families a Merry Christmas & a Happy new year!

Shenstone School TKAT ACE

As we approach the holiday season, we wanted to provide you with the latest update on the progress of the school’s const...
11/12/2024

As we approach the holiday season, we wanted to provide you with the latest update on the progress of the school’s construction. Here’s where we stand with each building:

Building 4
Screed: Levels 1 and 2 completed by Direct Screeding.
Green Roof: Installed by Ashtec.
Windows: First-floor installation complete; ground-floor work underway with Sealtite.
Brickwork: Preparations nearly complete for Eco Brickwork.

Building 2
Partitioning: Completed in the existing section by CPC.
Roof Joists: Installation in the new extension progressing with Maple.

Building 3
Roof: Installation has started by Ashtec.
Sports Hall Stores: Infilled by Tamber.
Partitioning: Nearing completion by CPC.

Building 1
Windows & Doors: Fully installed by Sealtite.
M&E Work: Progressing well with Pentalec and Delta.
External Cladding: Approaching completion by CPC.
Fire Protection: Work has begun across all floors with CA Fire.
Roof Coping: Completed by Ashtec.

This is our last update before Christmas, and we’ll continue to keep you informed as the project progresses into the new year.

Shenstone School TKAT ACE

Shenstone School Project UpdateWe've reached some significant milestones at Shenstone School, working alongside London B...
25/10/2024

Shenstone School Project Update

We've reached some significant milestones at Shenstone School, working alongside London Borough of Bexley.

The new SIPS building for Block 4 is really taking shape. Working with Innovaré Offsite Limited, we've completed both the ground and first floors. Roof cassette installations are underway, and we expect to finish by the end of next week, allowing us to proceed with making the roof watertight and installing windows.

While Block 4 progresses quickly, the existing building has also seen major advancements. Together with Clean Slate Demolition, we completed demolition and asbestos removal. ASHTEC ROOFING have levelled and completed the watertight roof. CPC Interiors are now on-site, working on boxing in the perimeter and boarding ceilings. Next up: window installation and M&E work.

Over at Block 2, we’ve got the block and beam foundations in place, and block walls are going up now with Floorspan Contracts.

A huge thanks to everyone involved, both on-site and behind the scenes. We look forward to sharing more updates as the project moves forward.

Project team, Nathan C***s, Darran Richardson, Robert King, Tom Noctor, Mark Parmenter, Brandon Waters, Laura Downing, Sam Pateman, Holly Hulme, Paul Khatkar, Steph Harris & Sasha Silk.
Photo credit - Nick Johnson

TKAT ACE

We are thrilled to announce that we have successfully completed the project this week! The 6 new classrooms, toilets, th...
30/08/2024

We are thrilled to announce that we have successfully completed the project this week! The 6 new classrooms, toilets, therapy room, staff room, reception and accessible ramps and doors are all ready to welcome your children back next week. Here's a sneak peek at the temporary accommodations your children will enjoy while work continues at a swift pace on the Halt Robin Road site!

Executive Head Teacher Lori visited Jubilee School yesterday and shared her thoughts:

"I am blown away by the Jubilee site and even more optimistic about the outcome for our permanent home at the Halt Robin Road site."

We hope you all enjoy your visit to the school and look forward to sharing more progress on Halt Robin Road very soon!

Shenstone School TKAT ACE

Construction Progress Update at Belvedere Site! 🚧We’re excited to share the latest developments from the Belvedere site....
20/08/2024

Construction Progress Update at Belvedere Site! 🚧

We’re excited to share the latest developments from the Belvedere site. The concrete slab was successfully poured and has now set, allowing us to start erecting scaffolding. In the next month, we’ll be gearing up for the delivery of SIPS (Structural Insulated Panels), which will be a major milestone in our build process.

You might be wondering, what exactly is a SIPS building? We’re collaborating with Innovare Offsite, a company based in Coventry, to bring this innovative construction method to life. SIPS are prefabricated high-performance panels, built offsite and designed to offer exceptional load-bearing capacity, structural integrity, thermal performance, fire resistance, and acoustic performance.

These panels replace traditional steel or concrete structures with a lightweight timber frame, which includes internal and external walls, floors, and roofs. Not only do they provide a complete dry structure, but they also speed up the construction process, opening up more opportunities for clever value engineering.

Once the panels arrive on site, they’ll be lifted into place with a crane, transforming the site quickly and efficiently. Stay tuned for more updates as we move forward with this exciting phase of the project! 🏗️

Shenstone School TKAT ACE

We are thrilled to share an exciting update on the construction progress at our Belvedere site. Yesterday marked a signi...
01/08/2024

We are thrilled to share an exciting update on the construction progress at our Belvedere site. Yesterday marked a significant milestone as we completed the concrete slab pour for the new SIPS building. This follows the completion of ground works and is a major step forward in our project.

Incredible teamwork was on display as 20 lorries delivered cement continuously, connecting to the pour machinery. The team expertly controlled the pour, using vi*****rs to eliminate air bubbles and flattening the concrete for a smooth finish.

Once the concrete has dried, we will shutter the sides, and scaffolding will commence on 19th August. The new school building components are scheduled for delivery starting 10th September will be built on top of the concrete.

Our drone photographer will be capturing these developments, allowing us to share the building's progress visually with you.

In addition to the new building, we are actively working on refurbishing the existing structures. Block work is underway in Building 1, with significant progress in the sports hall and Building 2.

Stay tuned for more updates! We will be posting next week with further progress reports from Jubilee. As always, if you have any questions or enquiries, please feel free to contact us. We are here to assist you.

08/07/2024

Progress is underway at Jubilee Primary School, where temporary facilities for your children are being prepared during the construction of Shenstone Belvedere. Attached is a video showcasing the spaces we have been preparing before commencing the renovation work. Following the video, substantial efforts have been focused on the refurbishment of these areas.

Keep your eyes peeled for updated footage!

If you have any queries, please reach out!

Shenstone School

Hi everyone,The reduce level dig for Block 4, our new build area, is complete. The ground has been levelled and prepared...
18/06/2024

Hi everyone,

The reduce level dig for Block 4, our new build area, is complete. The ground has been levelled and prepared for the foundation work to begin. We expect the new SIPS building to arrive in August, and we can't wait to share photos of its progress with you.

In Block 1, construction is moving along well. The scaffolding is up, allowing us access to the roof for stripping and the installation of the new roofing, which will start next week.

Over the next few weeks there will be lots of changes, keep your eyes peeled for updates! Should you have any questions or concerns, please don't hesitate to reach out. We look forward to providing you with further updates in the near future.

Shenstone School

🌟 Meet the Shenstone Belvedere Site Team! 🌟Introducing the incredible team behind the scenes making everything happen at...
14/06/2024

🌟 Meet the Shenstone Belvedere Site Team! 🌟

Introducing the incredible team behind the scenes making everything happen at the Shenstone Belvedere project:

🔧 Mark - Our Operations Manager is overseeing this entire project, ensuring the programme runs smoothly and efficiently.

🔨 Nathan & Darran - Both are based on-site, managing the day-to-day build and making sure all works are completed to the highest standards.

🎨 Brandon & Holly - Brandon, our Senior Design Manager, along with Holly, his Assistant Design Manager, work closely with the design team. They ensure that every technical detail complies with the school's brief.

📊 Paul & Sam - Our Quantity Surveyor on site, is responsible for placing orders with subcontractors, expertly assisted by our QS trainee, Sam.

🌱 Tom - Our newest addition, Tom, is a Management Trainee Apprentice. He’s gaining valuable experience by working alongside all of our talented team members.

We are always here if you have any queries about the build.

SShenstone School

Since our last update, there has been significant progress on site at the new Shenstone School.Demolition of the 5 prefa...
24/04/2024

Since our last update, there has been significant progress on site at the new Shenstone School.

Demolition of the 5 prefabricated buildings has been completed along with works on the retaining walls. Whilst the soft strip-out process for the retained buildings has been finished, paving the way for structural repairs and alterations scheduled throughout May.

This week, we're pleased to announce the delivery of our welfare and site cabins, which will be fully operational by the end of April, serving as the base for our team throughout the project.

Should you have any questions or concerns, please don't hesitate to reach out. We look forward to providing you with further updates in the near future.

Shenstone School

Address

Apex, The Old Mill
Bexley
DA51JX

Alerts

Be the first to know and let us send you an email when Shenstone School Project, Belvedere - Apex Contractors Ltd posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Shenstone School Project, Belvedere - Apex Contractors Ltd:

Share

Category