Some progress we have made this week on a job we are carrying out for a good friend of ours.
Works completed so far include;
Removal of structural wall to turn two rooms into one open space.
Removal of external wall and installation of RSJs for fitting of bifold doors.
Removal of external walls below bay windows for fitting of floor to ceiling windows.
Waste pipes installed for kitchen where required.
Boxing out of ‘floating ceilings’ this includes stud work, boarding and plastering.
Walls boarded where required and plastered throughout.
Full electrical installation for anything required in the new kitchen. outlets for all appliances and all new lighting.
Still ongoing but very close to handing over to the kitchen fitters.
We are just as excited as the customers to see the final outcome, which will come just in time for Christmas.