TORRI TIR LTD Civil Engineering & Land Surveying

Aldi Cardigan from start to present 6 weeks
02/06/2026

Aldi Cardigan from start to present 6 weeks

28/05/2026

Trief kerbs going in, one end of site and retaining wall on the opposite side 👍

27/05/2026

Aldi Cardigan - Retaining walls being positioned, steel frame completed, car park kerbs at 80% complete

New Aldi build in Cardigan, some arial shots from the helicopter 🚁
23/05/2026

New Aldi build in Cardigan, some arial shots from the helicopter 🚁

22/05/2026

Aldi Cardigan steel frame completed and kerbs well underway

12/05/2026

Aldi Cardigan steel progressing and final set of pile caps and ground beams going in

11/05/2026

Aldi Cardigan final concrete foundations dug and piles being cropped, steel erectors starting with frame work

Aldi Cardigan first of the foundations being poured today, holding down bolts set
06/05/2026

Aldi Cardigan first of the foundations being poured today, holding down bolts set

New Aldi Cardigan piles cropped, ground beams and pile caps set out
04/05/2026

New Aldi Cardigan piles cropped, ground beams and pile caps set out

Aldi Cardigan cesspool located and manholes formed
23/04/2026

Aldi Cardigan cesspool located and manholes formed