π§ What a difference a week makes at Tees Valley School! π§
Progress is moving at pace on our earthworks package for BAM UK & Ireland, with another productive week on site.
Over the last seven days, our team has:
β
Levelled off the site ready for the next phase of construction
β
Started excavating for the attenuation tank installation.
β
Constructed the MUGA (Multi-Use Games Area) base.
Sustainability continues to be a key focus throughout the project. Wherever possible, we're recycling materials on site, reducing waste and making the best use of available resources while minimising unnecessary vehicle movements.
With the recent dry weather creating challenging dusty conditions, we've also introduced a tractor and water bowser to suppress dust, helping to protect our workforce, neighbouring residents and the surrounding environment while keeping the site operating safely and efficiently.
It's fantastic to see the transformation taking shape already, and we're proud to be laying the foundations for a modern specialist education facility that will benefit the Tees Valley community for years to come.
A big thank you to everyone on site for another safe, productive weekβwe're looking forward to sharing more progress soon.