17/06/2026
Busy start to the week , with the added annual vans to be serviced at the same time .
On the Lydiate job we have been doing the roofing works carried out and awaiting to lay the tiles to the porch roof as the supplier delivered the wrong ones, so we sorted the valleys out to the main roof and fascia / soffits all done ready for the next steps.
Window removed ready for the next part to open into the porch.
Then, on the west derby job , started the kitchen fit and problem solving the issues with the soild brick walll being 6 inches away from the metal studwork and the corners being 3 inches out of square!
But all are looking well on this one 👌 .
Now for a well deserved night off watching England open up their campaign in the World Cup with a win. Come on England.