NEW PROJECT- remove existing loft and create Master bedroom with en suite.
With consent by the adjoining home owner Aintree were given position to remove the large shared dis used chimney stack, this will en able the dormer to be set 500 mm from existing position creating more space. Removal of the stack is also beneficial to the neighbour, as in the future they can also creat more space with in there conversion.
Monday -strip roof, steel install, felt front elevation, temporary cover to rear.

PASSED by building control today, loft ready for painting. 6.5 weeks from Scaffold install. 65 m2 loft space- 6 m2 bathr...
14/10/2026

PASSED by building control today, loft ready for painting. 6.5 weeks from Scaffold install. 65 m2 loft space- 6 m2 bathroom -stairwell - 20 m2 storage.

Thanks to All the Team & suppliers

# loftconversion

BUT WE DO NOT WANT A NEW ROOF- was the response before the explanation. Now Aintree could have patch up, re used 1980 ‘s...
04/10/2026

BUT WE DO NOT WANT A NEW ROOF- was the response before the explanation. Now Aintree could have patch up, re used 1980 ‘s interlocking tile, found colour match for rear dormer, not renewed the gutters, put plastic fascia/sofit on, breather vent to inter locker as per drawing. “Just to win a Job”

However the home and road deserved more.
-desirable location
-period property
-40 year old failing roof to which under felt will not breath correctly for new insulation air flow.
-large sections would need to be removed for construction, new valley, hips to meet engineers specification.
-savings on steels/calculations for steels and complete beams can be installed.
-leave failing lead bays to front elevation.

The explanation was valid and the out come delivered.

-new Marley machine made clay plan tiles, Haris hips, decorative bonnets, on breathable felt.
-hardwood fascia and sofit, to dormer & rear, existing sanded filled painted black.
-front elevation painted black.
-large velux over stair well
-grained sliding sach windows
-new gutters
-new lead bays.

Would you have taken Aintree’s advice ?

Thank you to all the Team

LOFT READY for plastering, the Team are currently 4 weeks into this large Upminster conversion. External roof near compl...
27/09/2026

LOFT READY for plastering, the Team are currently 4 weeks into this large Upminster conversion. External roof near completion., stairs installed this week, windows installed, first fix plumbing complete, plaster board complete, scrimed.

MAIN FRAME complete & passed this week - insulation under way stage 1 complete -100 mm PAR ceil-75 mm PAR. External wall...
13/09/2026

MAIN FRAME complete & passed this week - insulation under way stage 1 complete
-100 mm PAR ceil
-75 mm PAR. External walls.
-SF 40 to rafters

11 Days from stripping

Week ahead

-external roof works begin
-install velux x 3
-fasica & sofit
-chip board flooring
-2nd stage insulation
-insulation inspection
-first fix Electrics
-plaster boarding

CROWN DORMER external frame complete - Strip exist roof tiles- felt & cover- preparation for steels - Steel install with...
06/09/2026

CROWN DORMER external frame complete - Strip exist roof tiles- felt & cover- preparation for steels - Steel install with Moblie Crane - construct rear dormer - felt & cover - 5 days

Steel supply The Steel Team
Waste removal Sharp Group
Roof strip Miles Burgess

WHERE ARE AINTREE NEXT ? - a prime location in Upminster. The Team are set to create a new master bedroom with en suite ...
28/08/2026

WHERE ARE AINTREE NEXT ? - a prime location in Upminster. The Team are set to create a new master bedroom with en suite with wardrobe. The home is set for a full re roof - Marley plain tile with decorative bonnets.

19/08/2026

LATEST Upminster conversion ready for painting. 4.5 weeks- ground floor wall reinstated to meet Building Regs, fire Doors complete, ensuite ready for Mastic - Building control booked for tomorrow. Scaffold removed.

CURRENT CONVERSION- scaffold booked to be removed- good clean- mastic- remove ⬇️⬇️⬇️Marley grey interlocking Tile to Mai...
11/08/2026

CURRENT CONVERSION- scaffold booked to be removed- good clean- mastic- remove ⬇️⬇️⬇️
Marley grey interlocking Tile to Main Roof Marley plane Tile to Dormer - 1.5 mm silicon render to side elevation- black facia - white soffits -half round gutters-Mk 04 velux x 2 -White UPVC Windows. 3.5 weeks from removal of tiles.
Thanks to all the Team.

NEW EN SUITE- Villeroy & Boch full suite - 800 x 1800 shower tray - 600 sink unit with basin- Tap - wall hung pan - 800 ...
07/07/2026

NEW EN SUITE- Villeroy & Boch full suite - 800 x 1800 shower tray - 600 sink unit with basin- Tap - wall hung pan - 800 x 800 wall and floor tiles - 1800 x 200 niche - flush mirrored cupboard- duel fuel radiator. Ready for colour match mastic to be applied.

Address

Upminster
Upminster
RM14

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm
Saturday 9am - 2pm

Telephone

+447968072697

Alerts

Be the first to know and let us send you an email when Aintree Lofts posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Aintree Lofts:

Shortcuts

Sponsored

Share