28/10/2026
READING A PUMP CURVE: DUTY POINT, EFFICIENCY, POWER, AND OPERATING LIMITS
A pump can deliver the required flow and head—and still be a poor selection.
Before approving a chilled-water pump, check where it operates, how much power it requires, and whether its operating range is acceptable.
Here is a practical approach.
1️⃣ START WITH THE CORRECT CURVE
Confirm the curve matches the proposed:
• Pump model.
• Impeller diameter.
• Rotational speed.
• Fluid and operating conditions.
Check the units carefully. Flow may be shown in L/s, m³/h, or US gpm; head may be in metres or feet.
A curve for a different speed or impeller is not interchangeable with the selected pump’s curve.
2️⃣ FIND THE REQUIRED DUTY POINT
The design duty specifies:
Q = Required flow
H = Required pump head
Example:
Q = 20 L/s = 72 m³/h
H = 20 m
Locate 72 m³/h on the horizontal axis and 20 m on the head axis.
This identifies the required design point.
However, the actual operating point is where the pump curve intersects the system curve at the current speed and valve positions.
Selecting a pump that produces more head at the required flow does not guarantee it will deliver exactly that flow. The operating point must be established through the system resistance and controls.
3️⃣ CHECK EFFICIENCY AND THE BEP
The Best Efficiency Point, or BEP, is the point of maximum pump efficiency for the selected configuration.
Read the efficiency at the actual duty point—not simply the highest efficiency printed on the chart.
For this worked example, assume:
Pump efficiency at duty = 75%
This is an illustrative assumption, not a manufacturer selection.
A good selection considers both the design duty and the hours spent at other operating conditions. This is especially important in variable-flow chilled-water systems.
4️⃣ CALCULATE THE THREE DIFFERENT POWER VALUES
Assume:
• Water density = 1,000 kg/m³.
• Flow = 0.020 m³/s.
• Head = 20 m.
• Pump efficiency = 75%.
• Motor efficiency = 90%.
A. Hydraulic power delivered to the water:
Pₕ = ρ × g × Q × H
Pₕ = 1,000 × 9.81 × 0.020 × 20
= 3,924 W
= 3.92 kW
B. Shaft power required by the pump:
Pshaft = Pₕ ÷ ηpump
Pshaft = 3.924 ÷ 0.75
= 5.23 kW
C. Electrical input to the motor:
Pelectrical = Pshaft ÷ ηmotor
Pelectrical = 5.232 ÷ 0.90
= 5.81 kW
If a VFD is installed, its losses must also be included when estimating supply-side electrical input.
The distinction matters:
• 3.92 kW reaches the water.
• 5.23 kW is required at the pump shaft.
• 5.81 kW enters the motor under these assumptions.
Check the manufacturer’s legend: a published power curve may show shaft power or electrical input.
5️⃣ DO NOT SIZE THE MOTOR FROM ONE POINT ONLY
A 5.23 kW shaft requirement at design duty does not automatically justify selecting a 5.5 kW motor.
Check the maximum absorbed shaft power over the intended operating range, including permitted speeds and flows.
Also consider fluid density, applicable derating, and the manufacturer’s selection requirements.
Motor nameplate kW normally describes rated mechanical output—not constant electrical consumption.
6️⃣ CHECK THE OPERATING LIMITS
BEP is a reference point. It is not the complete operating envelope.
Review:
• Preferred Operating Region (POR): the preferred range around BEP for efficiency and reliability.
• Allowable Operating Region (AOR): the wider manufacturer-defined operating envelope.
• Minimum continuous flow: respect applicable hydraulic and thermal limits.
• Maximum permitted flow: the far-right end of a plotted curve is not automatically an approved duty.
• Shutoff head: head at zero flow, important for maximum-pressure checks.
• Maximum speed and power: particularly with VFD operation.
Do not assume one percentage range around BEP applies to every pump.
7️⃣ CHECK NPSH SEPARATELY
Read the required NPSH at the relevant flow, then calculate available NPSH from the actual suction conditions.
Provide the margin required by the manufacturer and applicable guidance.
Where the curve shows NPSH3, it represents a test condition with a 3% head reduction caused by cavitation. It is not a “no cavitation” boundary.
Matching NPSHa to NPSH3 is therefore not an adequate selection target.
✅ BEFORE APPROVAL, ASK:
Does the pump meet the required duty?
Is normal operation within the preferred region?
Is the motor adequate across the intended range?
Are suction conditions and NPSH margin acceptable?
Are minimum flow and maximum pressure addressed?
💬 Which detail is most often missed in pump submittals: duty-point efficiency, absorbed power, or operating limits?
References:
• Hydraulic Institute: Pump Curves; Pump System Operating Point.
• Hydraulic Institute: The Basics of NPSH & Pump Operating Regions.
• Grundfos: Basic Hydraulics and Pump Performance.
MEP Engineers Club
www.mepengineersclub.com
Er. Qasim Ibrar