04/18/2026
Miagatter project is close to being totally done. This is a good size project and everyone has come together to get this on track once we were asked to be the General Contractor/Builder. Remind you we got brought in at the last moment in October and Started the framing on 11/6/2025
The painting and staining is being done on all the trim, windows and doors which started last week on phase 2 of the existing cabin renovation with a few things still needing done in the addition painting wise on trim. This has been a 85% gut because of water leaking for years before the Miagatters purchased this place. They’re turning it into their forever home up north retreat.
Phase 1 was adding on a 3500sf addition/garage/bonus room.
The stone work with start once we can get materials in when things dry up.
Tile work will be starting soon on the bathrooms, do washing station and great room.