04/11/2021
CONSTRUCTION UPDATE: The following work will begin or continue the week of April 12, weather permitting.
ASPHALT
• Kickapoo Drive
• Sauk Drive
• Riverside Park (BMX Lot)
Patching (then Paving later in the year)
• Camomile Lane
• Grist Mill Drive
• Morning Sun Lane
• Old Ivy Drive
• Whisper Walk Drive
• Woodmore Drive
CONCRETE WORK
• Barons Road
• College Street (South Grand - Cook)
• Eagle Wing Road
• Deer Head Lane
• Millstone Drive (Meadowbrook - Eagle Wing)
• Mountain View Drive
• Quarterstaff Road
• Roundtable Road
• Westgate Drive
SIDEWALK REPAIRS
• 431 East Adams Street
• 2605 Chicory Drive
• 2105 South Disar Drive
• 2025 West Montford Court
• 82 Trailbridge Lane
• 3601 Wexford Drive
• Jefferson and Lincoln
• Seventh Street (Scarritt - Clay)
ALLEY REPAIRS
• 12th/13th - Jackson/Capitol
• 15th/16th - Jackson/Capitol
• 13th/14th - Edwards/Cook
PARKWAY REPAIRS (including rock, ditching, culvert repairs)
• 1842 South 19th Street
• 502 West Carpenter Street
• 214 South David Street - even side from Adams to Monroe
• 1837 South Dial
• Edwards/Wheeler - northwest corner
• 504 South White City
FORESTRY WORK
• 464 West Cook
• 2300 South Sixth
• 202 North State
• 301 South State
• 1520 E. Matheny
• 1129 North Milton
• 2000 South Montague
• 304 South Park
• 1318 East Pine
• 1304 East Pine
• 1302 Wiggins
I-72 BRIDGE MAINTENANCE BEGINS APRIL 12 AT SIXTH, SECOND STREET
Illinois Department of Transportation announced crews will begin washing and painting bridges on Interstate 72 at Sixth Street and Second Street beginning April 12. Work will begin at Sixth Street, which will be reduced to one lane in each direction. When Sixth Street is complete, by approximately June 1, the project will move to Second Street. Second will be closed periodically between June 1 and September 1 for a total of 30 days, with nighttime lane closures on I-72. All construction is expected to be complete by September 1.
ONGOING WORK & CONTRUCTION....
GRADING AND DITCHING
Archer Elevator Road (Grading)
Hilltop Road Trail Extension (Ditching and Grading)
LANE CLOSURES ALONG THE FORMER DOWNTOWN YMCA
Lane reductions are in place around the former downtown YMCA until April 23.
SOUTH WALNUT DETOUR CONTINUING
The northbound traffic lanes on Walnut Street, between South Grand and W. Canedy are still closed. This is to accommodate water service line improvement work. Work for this section should be completed by the end of the day on April 16.
DRAWBRIDGE ROAD
Complete riprap installation and abutments. The city anticipates the project will be done sooner; however, the contract completion date is thru August.
LENHART ROAD IMPROVEMENTS
Seeding, grading at Lenhart & Bunker Hill
FIFTH AND SIXTH STREET UNDERPASSES
Installing drainage structures
***6th Street reduced to 3 lanes northbound: Wellesley - Broad***
LAUREL STREET UNDERPASS
Closed through July 31, 2021
Currently installing abutments, Union Pacific Railroad over Laurel.