Passivo Construction

Passivo Construction Established in 1989 Newcastle Home Construction Corp is the mot trusted name in general contraction in the Rochester Area

This is the current phase on construction. Quarter sawn white oak floors are installed, an additional window for the lau...
09/05/2023

This is the current phase on construction. Quarter sawn white oak floors are installed, an additional window for the laundry room was ordered and the final installation is now complete. We are counting down the days, anticipating a mid October completion. By the way our blower door test came in under 2.

Here is an update on my Keuka Lake project, on E. Bluff Dr. Pictures are from June to last week. Including finished fram...
09/04/2023

Here is an update on my Keuka Lake project, on E. Bluff Dr. Pictures are from June to last week. Including finished framing, insulation, drywall and trim. More pics to come. Thanks for following me.

Great progress this week including   panels installed, siding nesting completion and deck railing installed.
06/25/2023

Great progress this week including panels installed, siding nesting completion and deck railing installed.

Progress everyday at our   project. Gas line installation and siding is nearing completion.
06/15/2023

Progress everyday at our project. Gas line installation and siding is nearing completion.

The Martin home from the lake this past week, deck envoys the latest buzz.   and   are two components that will make thi...
06/05/2023

The Martin home from the lake this past week, deck envoys the latest buzz. and are two components that will make this home super efficient. Notice the vertical tape with no horizontal seams, cutting down on air infiltration by installing 10’ … a small detail that has a significant impact on any homes energy efficiency and comfort.

Our city project is also moving along rapidly with Tile and Trim being worked on this past week. Counters go in Wednesda...
05/26/2023

Our city project is also moving along rapidly with Tile and Trim being worked on this past week. Counters go in Wednesday and then the final tile backsplash shortly there after.

Roofing complete and rough mechanicals have started. We are on schedule and moving towards anticipated completion in Oct...
05/26/2023

Roofing complete and rough mechanicals have started. We are on schedule and moving towards anticipated completion in October. Next on the schedule is window installation, HVAC, plumbing, electrical and low-voltage rough in to be completed next week.

Here’s a look at a renovation project that we are in the final stages of construction, I’ve been renovating a house in t...
05/17/2023

Here’s a look at a renovation project that we are in the final stages of construction, I’ve been renovating a house in the suburbs and this is a real catch up. We tore out the existing kitchen, removed an existing structural wall and repositioned an interior wall to add a master bath with double vanity. Look towards the next post to see our most current activity.

A lot of framing to catch up on…  was ordered in 10’ lengths so eliminate horizontal seems resulting in a tighter more e...
05/17/2023

A lot of framing to catch up on… was ordered in 10’ lengths so eliminate horizontal seems resulting in a tighter more energy efficient structure. Subfloor is 3/4” panels. Roofing will continue Friday and next week we start plumbing and HVAC rough in. The schedule has slipped a little due to rain a few weeks ago however good progress is being made and we should be able to catch up over the next few weeks, stay tuned

Rain has delayed construction over the past week, however it appears that clear skies are forecasted for next week and t...
05/05/2023

Rain has delayed construction over the past week, however it appears that clear skies are forecasted for next week and trusses have been rescheduled for Wednesday. All interior walls are up and focus will turn to lower level walls, exterior sheathing and deck framing.

Good progress last week with the first floor deck in place we had a couple of sunny days to backfill the foundation and ...
04/26/2023

Good progress last week with the first floor deck in place we had a couple of sunny days to backfill the foundation and load crushed stone into the garage and main entrance porch foundations. We also installed the egress well that will be connected to a lower level bedroom. The egress well was backfilled with stone which will allow water to percolate down to the and thru the underground conductor to the lake. Wall framing starts tomorrow

Progress this week included laying down an R20 insulation under slab 4 inch concrete floor reinforced with steel mesh an...
04/15/2023

Progress this week included laying down an R20 insulation under slab 4 inch concrete floor reinforced with steel mesh and power troweled for a level finish.

Address

207 Rutgers Street
Rochester, NY
14607

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm
Saturday 8am - 5pm
Sunday 8am - 5pm

Telephone

+15852020479

Website

Alerts

Be the first to know and let us send you an email when Passivo Construction posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share

Category