🏫 School Demolition Case Study
Thanks to our friends General Contractors we Completed a phased demolition project at a school facility during a full campus shutdown.
Even without students or staff onsite, the work required strict coordination, cleanliness standards, and careful sequencing to prepare the buildings for renovation.
Scope:
Interior selective demolition
Classroom and common area strip-out
Full debris removal and cleanup
Challenges:
Tight project schedule for turnover
Protecting existing structure and systems to remain
Maintaining clean, controlled jobsite conditions for follow-on trades
Ex*****on:
Organized phased demo plan by building zones
Continuous debris haul-off to maintain access and safety
Clean final sweep for renovation readiness
Result:
Project completed on schedule with a clean, fully prepped facility ready for rebuild.