13/08/2026
👏 July Update: Proudly sharing our progress and a few shots for July 2026, from Palais Bulimba development site, by Zephyr Group Qld.
+ The basement rendering is now underway.
+ The level 2 south columns have now been poured, with structure continuing to progress.
+ The feature facade, located on level 3, is now fully formed and ready for the upcoming concrete pour.
+ The formwork located in the level 1 south apartments has now been removed.
Zephyr Group Qld, has advised that anticipated completion at this stage is forecast for the end of Q1 / start of Q2 next year.
We look forward to providing you with further monthly updates and site progress photos as further progression takes place on site.
Visit Palais Bulimba here https://www.palaisbulimba.com.au/