👏 April Update: Proudly sharing our progress and a few shots for April 2026, from Palais Bulimba development site, by Zephyr Group Qld.
1. The northern ground floor wall installation is now complete, with the level one formwork now in place.
2. The final southern ground floor columns are now completed, marking structural progress.
3. The entry stairs and planter blockworks are now completed.
4. The northern slab on level one has now been successfully poured.
Stay tuned for more Palais Bulimba updates as we move closer to unveiling luxury living at its finest! 🌟
If there is anything we can do to assist you, please don't hesitate to reach out.