23/06/2026
235 Napier | Basement works progressing.
Significant progress continues at 235 Napier, with Basement Level 1 excavation and shotcrete works now complete.
With the first basement level secured, the team has now shifted focus to preparations for Basement Level 2 shotcrete, marking another key step in the project's below-ground construction sequence.
Another important milestone delivered as the team continues building momentum on site.