Project Completion | Beaumont Care, Clontarf QLD
We're proud to announce the successful completion of the refurbishment of a 21-bedroom aged care home for Beaumont Care.
Delivered within a fully operational care environment, the project involved the refurbishment of resident bedrooms, ensuites and three decanting rooms across six carefully planned stages. Every aspect of the works was coordinated around daily resident routines, personal care requirements and meal services to ensure minimal disruption and continuity of care throughout construction.
A key project innovation saw the consolidation of Stages 5 and 6 within the same segregated wing, reducing programme duration and limiting repeated disruption for residents and staff.
Despite challenges including existing site conditions, material lead times and fixture performance issues, the team maintained a strong focus on quality, communication and collaboration, achieving completion in just 40 weeks.
Congratulations to Glenn Ricketts, Greg Cutler, Chris Faure-Field and Kim Smith on a successful project delivery.
Read more: https://www.totalconstruction.com.au/blog/project-completion-beaumont-care-clontarf-qld/