30/03/2026
Project Complete – for bp Pulse, 214 Sydney Road, Kelso, NSW
EV Fast Charging Site Complete!
Team Reslec have provided the turn key delivery for this project – as the ASP1, ASP2 and the electrical contractor for the project.
Complete package delivery –
- early planning
- service scanning
- all civil construction works - service locating/ Non Destructive excavation, all mechanical excavation, duct installation as per the certified and IFC Design, underbore works, inc concreting and bollards
- Linemarking works
- ASP1 Construction and delivery – 1Mva transformer, HV and LV cabling and associated Jointing works
- ASP2 Service Connection – to the new 1Mva transformer, and service commissioning
- Area lighting – with 2 x new LED column lights to illuminate the charging area
- 3 x new Alpitronics Hyperchargers, and a new
- Supply and installation of a new custom Main Switch board for the site
- Customer genset – to facilitate the operation of the site during the outage and changeover program
- Testing and commissioning of the site
- Landscaping and re instatement works
Proud delivery of this project for bp Pulse!
”