🧱 TUESDAY WAS ALL ABOUT GETTING THE DAY IN 😜😂
Today’s job wasn’t actually supposed to be ready until tomorrow.
No cement.
No scaffold.
No door frames.
Not much really. 😂
Everything was due to arrive tomorrow, but we couldn’t finish Yanchep because we were still waiting on the front window frame and some extra maxis.
And with tomorrow looking like a complete washout, I was determined we were getting a day in somehow. 😂💪
So we collected scaffold and cement from another job, loaded the van up and basically just made it work with what we had. 🧱😂
Considering what we started with this morning, we actually did pretty well and got a fair bit built. 👌
And amongst all that, we managed to try out one of the new string lines from BT Engineering as well. 👀🧱 Let’s see how that goes. 👍😂
And now, of course, tomorrow’s forecast has changed and it looks like we might actually get another day in. 🤔😂🌤️
Even better — the Yanchep window frame has JUST arrived. 🥳🥳
So we’ll be heading back there tomorrow to hopefully get that one moving again.
Thanks Dowells. 😂👍
Although… you’re not going to believe this.
Have a look at how the front elevation on TODAY’S job was left down. 👀😂
Dowells have done it again.
This time it’s not bent.
It’s not twisted.
IT’S JUST COMPLETELY THE WRONG FRAME. 😂😂😂
That’s now 3 jobs in a row. 😩😂
You honestly couldn’t make it up. 🧱😂