19/08/2021
Some photos of progress on site from our Fitout underway on Hay St.
All walls now erected, ready for painting
Electrical fit off 90% complete.
Plumbing first fix complete.
Kitchen & stone benches installed.
Glazed partitions installed.
Every remaining item ordered and en route.
All in an enjoyable 3 weeks.
Our client CSE Global (Australia & New Zealand) has access to our project management software, where they can view our schedule works, be notified of any updates, track costs & variations and add comments if required along the way.