Before the plaster goes on, a lot has to be right. This week that's exactly where the team was focused at 33 The Parade, North Haven.
Internal doors have started going in - DJ800 Intrim profile, hung with shadow line skirtings in place before any lining touches the walls. Frame inspection completed. Plumbing inspection done. Raked window frames arrived on site ready for glazing next week.
Next up: insulation this week, internal lining kicks off Tuesday, and raked glazing confirmed for June 19. It's all moving and the sequence is tight. That's how it should be.