18/06/2026
The $217.9 million Northern Midlands Irrigation Scheme is fast approaching completion. More than 150km of the 152km of pipeline is now installed and the Poatina buffer dam is full. The Poatina pump station has also been completed and has commenced pumping water, enabling the pipelines to be filled and tested across the scheme. The two balance tanks are complete and the final works on the other two pump stations at Valleyfield and Epping Forest are being finalised. This means up to 25,500 megalitres will soon be flowing to farmers throughout the Northern Midlands area, ensuring they can plan, plant, harvest, employ and generate additional wealth for the region and our State. Thank you to farmers, contractors, Hydro Tasmania and all other stakeholders for their ongoing communication and collaboration to ensure the project is ready to deliver water in time for the 2026/27 irrigation season.
Gavin Pearce Eric Abetz