Beginners Package Matroko Projects
Plan Design Drawing: P2,500.00
Bill Of Quantity: P1,500.00
_______________________________________________
BUILDING CONSTRUCTION - LABOR COST ONLY
SUBSTRUCTURE
Setting Out = P1,500.00
Digging = P4,000.00
Footing P5,000.00
Brickwork = P6,000.00
Backfill & Compaction = P3,000.00
Slab Concrete Casting = P11,000.00
Subtotal: P30,500.00
________________________________________________
SUPERSTRUCTURE
Brickwork Upto Window level = P22,000.00
Wall plate = P8,000.00
Roofing = P15,000.00 Both Blocks
Plastering = P18,000.00 Both Blocks
Subtotal: P63,000.00
________________________________________________
FINISHINGS
Ceiling = P9,000.00
Tiling = P15,000.00
Plumbing = P7,000.00
Motlakase = P10,000.00
Painting = P9,000.00
Doors & Locksets: P300 Per Door x 16 = P4,800.00
Subtotal: P54,800.00
________________________________________________
Grand Total Cost Labour: P148,300.00 Negotiable
Materials Cost: P160,000.00
Total Turn Key: P308,300.00 With Ablutions
Total Turn Key: P283,300.00 Without Ablutions