BEHIND THE SCENES π₯π₯π₯π₯
PLACE: Karakubis (over 700km from Gaborone)
PROFILE: Renovation, facelift plus extension
START DATE: July last year
The long run is largely due to the project being done in phases that include waiting periods.
WHAT DO WE LEARN FROM THIS PROJECT?
1. βοΈEndurance, resilience, reliability and unquestionable commitment.
2. βοΈ Despite the long run and unavoidable delays- we have never failed to show up once, and clients have never had the opportunity to complain or doubt our commitment.
3. βοΈIt's a joint effort. We communicate and solve problems together.
4. βοΈ All the fittings, finishes and glass were bought in Gaborone and delivered to the site by our truck.
5 βοΈ Again all these was possible through communication and joint family effort between client representatives and the company.
6. βοΈ Return trip to Karakubis costs P6,000 and we have been there 6 times already; total: P36,000 fuel alone before we include other expenses
7. βοΈYet we have never felt the need to take short cuts or find people we don't know nearby.