What’s new this week at Spire Development? 🏗️
At our Douglas Street site in Victoria, things are moving right along 👷♀️
• Drilling and blasting are starting in the southeast areas
• Hauling of soil and rock continues
• Waterproofing begins along the south wall
This project is well underway, and we’re happy to share there are no delays in sight 🎉
Over at Spire Landing 2 in Vancouver, there’s a lot of exciting progress happening:
• Patio door installations
• Electrical work
• PTAC grille installations (those sleek vents on the exterior)
• Ongoing sprinkler installation, waterproofing, spray foam, and elevator bracket work
With the wood framing completed, we’re looking ahead to our next big milestone, building envelope completion, projected for April 30, 2026 🏢
Progress you can see and momentum that keeps building. 💪
Stay tuned for more update👀👀