AXIS Shoring and Drilling

AXIS Shoring and Drilling Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from AXIS Shoring and Drilling, Construction Company, 4098 Lochside Drive, Victoria, BC.

861 Esquimalt Road | Perimeter Support Advancing ⚒️Our crew continues making steady progress at the 861 Esquimalt Road p...
06/18/2026

861 Esquimalt Road | Perimeter Support Advancing ⚒️

Our crew continues making steady progress at the 861 Esquimalt Road project as excavation support work moves along the perimeter.

With additional wall sections being sprayed and tiebacks installed throughout the excavation, the shoring system continues coming together to help stabilize the site for upcoming below-grade construction.

Great seeing multiple stages progressing together on this one alongside

06/17/2026

The Podium | Drilling Progress 🏗️

Our crew is advancing the last portion of the excavation shoring system at The Podium project alongside

Crews are currently installing tieback soil anchors to secure the upcoming shotcrete shoring as the site continues progressing toward design depth.

With drilling operations moving steadily across the perimeter, the team is also preparing for upcoming shotcrete application as the shoring system nears completion.

Another solid day of progress on site with multiple scopes continuing to move together.

06/05/2026

The Podium | Drilling Progress

Shoring crew is back on site at The Podium with The team is working along the ramp, drilling anchors across the perimeter to tie in the remaining sections of shoring.

These are some of the final pieces of work before the excavation is finalized, opening up the full footprint for building construction.

Every anchor, every pass, pushing the project one step closer.

06/04/2026

The Podium | Working Deeper

The crew continues pushing deeper at The Podium, advancing through the excavation shoring while installing shotcrete lift by lift along the site ramp.

Today’s focus is the Garnet Road wall, where precision and coordination are critical as each section is shot and shaped into place in preparation for parkade wall structural shotcrete.

Steady progress as we work toward final elevation across the site.

Working together with

ESQ Road | Drilling Operations Underway 🚧Work continues across the ESQ Road site as our crew pushes through multiple pha...
05/21/2026

ESQ Road | Drilling Operations Underway 🚧

Work continues across the ESQ Road site as our crew pushes through multiple phases of the excavation support scope.

Along the roadway perimeter, rock anchors are being drilled in to help secure the excavation, while vertical piles are being installed along the south side of the site to build out the shoring system.

Another solid push on site alongside

05/14/2026

ESQ Road | Multiple Fronts Moving ⚒️

Our crew is making steady progress across several areas of the Esquimalt Road project as the excavation support system continues to take shape.

Current work includes drilling rock anchors along the roadside perimeter, installing vertical piles on the south side of the excavation, and preparing wall panels for upcoming shotcrete application.

A lot of moving pieces coming together on this one alongside

ESQ Road | Shoring Progress 🏗️Shotcrete work continues along the Esquimalt Road excavation as our crew builds out the pe...
05/14/2026

ESQ Road | Shoring Progress 🏗️

Shotcrete work continues along the Esquimalt Road excavation as our crew builds out the perimeter support system section by section.

As tiebacks and shotcrete come together, the excavation is being secured and reinforced to support the next stages of construction below grade.

Good progress on site working alongside

05/13/2026

ESQ Road | Perimeter Support Underway 🏗️

Our crew continues advancing the shotcrete scope along the Esquimalt Road perimeter as the excavation support system takes shape.

With tiebacks being installed and wall sections sprayed into place, the shoring system is helping stabilize the excavation and prepare the site for the next phase of below-grade construction.

Another solid collaboration alongside as work continues to progress on site.

Esquimalt Road | Excavation Support Progress 🏗️ The .sd crew continues making steady progress at Esquimalt Road as the e...
05/13/2026

Esquimalt Road | Excavation Support Progress 🏗️

The .sd crew continues making steady progress at Esquimalt Road as the excavation support system takes shape across multiple areas of site.

Current work includes drilling and installing rock anchors along the roadside perimeter, setting vertical piles on the south side of the excavation, and advancing shotcrete application as sections of the shoring wall are built out.

With tiebacks, piles, and shotcrete all working together, each phase plays a key role in stabilizing the excavation and preparing the site for the next stage of below-grade construction.

Another solid example of the specialized work happening across the Mann Group alongside

05/11/2026

Luther Court | Securing the Perimeter 🏗️

Our crew is closing in on the final stages of perimeter shotcrete work at Luther Court, with the last wall sections along Cedar Hill now being completed.

With the tieback shoring system fully installed, the excavation has been locked in and stabilized, helping prepare the site for the next phase of construction below grade.

Great seeing another project come together alongside and

Address

4098 Lochside Drive
Victoria, BC
V8X2C8

Telephone

+12506866649

Alerts

Be the first to know and let us send you an email when AXIS Shoring and Drilling posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to AXIS Shoring and Drilling:

Share