🚧 Project Update – Wren Hall 🚧
One year on from commencing works at EGL2 Wren Hall, progress continues on one of the UK's most significant energy infrastructure projects.
Completion of the 24m-high slipform fire walls was achieved in February 2026. Since then, the Converter Building foundations have been completed, enabling structural steelwork to progress within the DC Hall of Converter Building 1.
Having completed the in-situ concrete edge beams to the Operations Building, we are now preparing to construct the ground slabs for both the Operations and Spares Buildings. Edge beam construction to the Converter Buildings is also due to commence later this month.
Last month, works began on the Spare Transformer structure with the successful completion of the 700mm-thick base slab and 1.9m-high bund walls. Additional structures remain under review as we continue to support BAM in delivering the wider programme.
⚡ Eastern Green Link 2 (EGL2) is a 525kV HVDC subsea transmission link connecting Peterhead in Scotland to Drax in England. With a capacity of 2GW, the scheme will be capable of powering up to two million homes and represents the UK's largest electricity transmission project to date.
Appointed by BAM UK & Ireland, Cidon Group is delivering the service buildings package, transformer and converter buildings, and associated structures.
Delivered as a joint venture between National Grid and SSEN Transmission, EGL2 is being constructed through the collaborative efforts of BAM UK & Ireland, Hitachi Energy and Cidon Group.
👏 A huge thank you to everyone involved for the continued hard work and commitment as we move confidently into the next phase of the project.