28/08/2026
🛤️Monsall to Central Park Track Renewal Scheme
✅ 14-day blockade completed
✅ 4,500 tonnes of material removed
✅ Track and drainage renewals successfully delivered
Working on behalf of Transport for Greater Manchester, our Story Track team successfully delivered a key phase of the Monsall to Central Park Track Renewal Scheme, helping to improve the long-term reliability and resilience of the Metrolink network.
🎥 Hear from Lee Carter, Jack Benton and Jennifer Evans as they reflect on the planning, collaboration and delivery of the project.