22/01/2026
PROJECT COMPLETION | RINGSEND WwTP, DUBLIN
LDC Electrics is proud to have completed a Large 21-month Electrical Retrofit Project at Ringsend Wastewater Treatment Plant, delivered for Uisce รireann, working alongside Murphy Group.
The works formed part of the Hybrid Package 2 SBR Blocks Retrofit, involving the decommissioning of existing plant systems and the design, supply & installation of new Power & control systems across 3No. SBR Blocks within a live operational plant serving Dublin city and surrounding areas.
Project scope included:
Fitting of MCC control panels
FRP & stainless-steel containment throughout.
Variety of cabling types for-Pumps, Motors, Valves and instrumentation
Cathodic protection systems
Building services & trace heating
Delivered continuously over multiple phases, with crews of up to 16-18 operatives at peak, this project contributes to improving the robustness and long-term performance of a critical national wastewater asset.
A major milestone completed โ well done to everyone involved.