Smart Joinery & Building

Smart Joinery & Building All aspects of Joinery

18/05/2026

Great project to be part of. Completed in stages throughout, every area of this renovation turned out beautifully. A fantastic effort from the whole team, and something everyone involved should be proud of!
- New dinning area
- x3 old bathrooms out x2 new in
- New utility room area
- Bespoke wardrobes
- New bedroom area

21/04/2026

Replacing existing roof ties to increase headroom within the space, using C24 timber, M12 bolts, and dog tooth connectors. On to the next room πŸ’ͺ🏼
Work will be carried out sequentially, replacing one tie at a time to maintain structural stability throughout the process πŸ‘·
contentcreator smallbusinessuk

20/04/2026

Big progress on site this week πŸ”§

Structural steel installed and opening fully prepped for the next stage!

Huge shoutout to the team for a solid Monday shift πŸ‘ Early start, great coordination, and everything executed safely and efficiently.

From steelwork ready for finishing details, it’s all coming together.
BuildingBetter OnSite MondayMotivation

17/04/2026

Diasen Diathonite Thermactive line bonding 90% done onto the next stage of this project!
Milestone getting built on to the levels needed πŸ’ͺ🏼

01/04/2026

We are cracking on with the lime and cork insulation system upstairs with build out up to 110mm in areas.
With the mesh layers completed today final pash out to get to required levels 🫑

28/03/2026

Been a good week with a Saturday shift πŸ’ͺ🏼

From…….
- Bespoke MDF cupboards
- Plastering lime cork insulation system
- Site work doing finishings

25/03/2026

3 days and almost there finishing touches tomorrow πŸ™Œ
Ready for the main man to get painting!

- bespoke MDF units
- custom integrated handles
- sensor LEDs to inside cupboard from
- oaks on order for centre shelves

07/02/2026

Utility room area ready for painting 🀝
Cladding (Osmo oil)
window & door (Anthracite gray)
- old bifold doors out
- new stud frame
- bespoke door
- new window
- cedar cladding installed

09/01/2026

Great first week back with the team πŸ’ͺ🏼

- strip out of flooring, plasterboard, electrical, plumbing and internal walls
- old concrete slab broken up and dug out 400mm from finished floor level
- x8 skips filled πŸ’₯
- new opening cut and concrete lintels fitted

All doors on this job with a smart joinery twist to them πŸ€“- Hidden door to utility room with soft closer - Side door wit...
08/12/2025

All doors on this job with a smart joinery twist to them πŸ€“
- Hidden door to utility room with soft closer
- Side door with clients spec, pattern to face of door
- Glazed French doors, with recessed pull handles to both sides

02/12/2025

Good shift today! πŸ€“
- old doors out
- stud frame built, osb and strapped ready for cladding
- bespoke window sill with matching door sill
- window fitted
- bespoke door to clients spec/design