🚨Progress update!
We’re making very good progress at the BT Data Centre site in Milton Keynes. All service terminations and asbestos removal is complete and we’re systematically demolishing all three buildings.
Over the coming weeks, we anticipate all remaining structures will be brought down, allowing us to move forward into the next phase of the project - substructure works, including the removal of ground slabs and foundations.