28/07/2026
200m Running Track – Base Preparation Complete
The 200m running track for the school has now been fully prepared for the wet pour surface.
Works completed include:
Track excavated to the required depth.
Approximately 80 tonnes of MOT Type 1 stone supplied and installed.
Base levelled and mechanically compacted ("whacked") to provide a solid, stable foundation ready for the wet pour installation.
The project is now prepared for the next stage of the surfacing works.