Broadway Builders We are a Building Company which specialises in extensions, loft conversions and refurbishments, commercial and residential. We offer free advice and quotes.

Please feel free to get in touch…
Simon-07798 780 105
Tom-07496 531 069 We are a team of 20+ which include full time tradesmen...carpenters, plumbers, electricians, bricklayers, roofers and decorators covering all aspects of the building trade. Allowing us to undertake large and small projects from beginning to end. We aim to take away as much stress from the customer by offering an extremely professional and reliable service. We can also assist with the drawings and planning applications. Over the years we have carried out works for the same customers as they move houses and a huge amount of our work is from recommendations.

Main road…This job is moving at a steady pace in the background whilst we have the others going at full steam…Both flats...
24/10/2026

Main road…
This job is moving at a steady pace in the background whilst we have the others going at full steam…
Both flats are now ripped out(pictures in next post), the scaffold is up and we can now begin the work to put the 3rd flat on top…

Slowing come to the end of our time at Roberts road…Due to all the bad weather we’ve had we managed to get a lot of the ...
24/10/2026

Slowing come to the end of our time at Roberts road…
Due to all the bad weather we’ve had we managed to get a lot of the internals completed,
All sticking and plastering is now finished, screeding completed with piped underfloor heating throughout, the customer is completing all second fix carpentry himself so all that leaves us with is the rendering, bathrooms and the landscaping.

Big update for Ashbourne…Over the last couple of weeks we’ve managed to completely first fix the new system extension an...
24/10/2026

Big update for Ashbourne…
Over the last couple of weeks we’ve managed to completely first fix the new system extension and existing rooms downstairs…
With the screeding completed we were able to get it all stuck and plastered ready for the kitchen and painting…
We managed to find a break in the clouds to fit the roof lantern, all 3 bathrooms are now ready for tiling which will be happening in a couple of weeks…
Both the loft and the middle floor have had the laminate fitted and now we can get skirting on.

Last week at Ashbourne….Flat roof first coated,Front and back pitched,Original downstairs floor ripped up,Plasterer is f...
05/10/2026

Last week at Ashbourne….
Flat roof first coated,
Front and back pitched,
Original downstairs floor ripped up,
Plasterer is flying,
Middle floor doors completed…

Now onto the over site and getting the doors and windows in

Last week at main road,The rip out of the the top flat is complete, we are at a stage where we can now prepare for the t...
05/10/2026

Last week at main road,
The rip out of the the top flat is complete, we are at a stage where we can now prepare for the third floor conversion…

Now the bottom floor!!!

Robert’s road progress,All the downstairs stud work is completed and electrics first fixed.Finished installing new windo...
26/09/2026

Robert’s road progress,

All the downstairs stud work is completed and electrics first fixed.

Finished installing new windows and plastered the original rooms.

Phenomenal week at Ashbourne, extension was finished and flat roof is completed. Doors on in loft and all plastering on ...
26/09/2026

Phenomenal week at Ashbourne, extension was finished and flat roof is completed.

Doors on in loft and all plastering on middle floor completed.

Steels arrived yesterday so the prep work to get the monster in has begun.

Next week we will get the pitch completed front and back👍🏻

Can’t complain with the progress being made on this job😮‍💨

Main road progress, lads have made great progress in hacking off walls and ripping the kitchen out, all ceilings have be...
18/09/2026

Main road progress, lads have made great progress in hacking off walls and ripping the kitchen out, all ceilings have been ripped down and all carpets have been taken up. Now we have a blank canvas to start work on with the middle floor flat.

Superb week at Ashbourne avenue😮‍💨 loads of progress made, dormer and first floor plastered. Scaffold finally down and t...
18/09/2026

Superb week at Ashbourne avenue😮‍💨 loads of progress made, dormer and first floor plastered.
Scaffold finally down and the job looks😍

Extension close to completion, next stage steels and knock through.

Address

Bexleyheath

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Alerts

Be the first to know and let us send you an email when Broadway Builders posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Broadway Builders:

Shortcuts

Sponsored

Share