28/05/2026
📍TKRE Tilbury
Since March 2026 , the team at CR Civil Engineering Ltd has been progressing a range of civils works across multiple locations, supporting access, infrastructure, and ongoing reconductoring operations. Working alongside Morgan Sindall Infrastructure part of the National Grid GGP scheme on the TKRE project.
Works have centred around the installation of temporary bridges, Trackway preparation, alongside continuous improvement / maintenance of haul routes to ensure safe and efficient site logistics. Significant volumes of Recycled Type 1 sub‑base and geotextiles have been installed, working within environmentally sensitive areas, the team has continued to operate under full ecological supervision, undertaking mitigation measures such as ant hill relocation, Root Protection, maintaining compliance within SSSI Assents & GCN Licences.
Despite challenges including constrained access routes, requiring changes to delivery methodology the team has adapted well to maintain programme progress across all work fronts.
A strong effort from all involved, continuing to deliver safely, efficiently, and to a high standard. & to our supply chain partners who have been detrimental to our delivery
RSK Habitat Management, Flannery Plant Hire, Synergy Hire Ltd, DIRECT SITE SUPPLIES LIMITED, GAP Group Limited, Pro Mech Ground Support Systems, Mark Ogburn , Heidelberg Materials, Gavin Griffiths , London Rock Partners, Natural England, NG Env team