02/07/2026
🚧 Current Project Update 🚧
Major groundwork progress on this new build project with the raft foundation installation now well underway.
Works completed include:
✅ Water supply upgrade
✅ Drainage installation
✅ Shuttering preparation
✅ Groundworks ready for concrete pour
This project consists of two raft foundation areas:
📐 Main raft – 133m²
📐 Secondary raft – 20m²
A lot of planning and preparation goes into getting the foundations right, ensuring a solid base for everything that follows. Looking forward to the next stage and seeing this project continue to take shape.
🏗️ Quality groundwork is the foundation of every successful build.