π§ SYCAMORE PROJECT | PART 7 β BIG PROGRESS, BIG CHANGES! π₯
Itβs been another busy one on the Sycamore Project! πͺ
β‘οΈ A little unexpected dramaβ¦ We managed to drill straight through a lighting cable! π¬ Thankfully, the repair is done and the lights are back on! π‘
β
Whatβs been completed?
π οΈ All plastering completed in the new area
π§± Brick skin removed and lintels installed on both skins of Doorway 1
πͺ Lintel fitted for Doorway 2
π‘ Internal blockwork removed to make way for the new patio doors
π Whatβs coming next?
π§± Brickwork at the front
πͺ Breaking through Doorway 2
π¨ Potential breakthrough for Doorway 1
π§Ή A BIG site clean-up!
Every stage brings us closer to transforming this space, and things are really starting to take shape! π₯π‘
π Want to see how it all comes together? Follow and stay tuned for Part 8!