🏗️ Weekly Update from The Best Build Team
Another Friday, another update from me 👋 It’s been a week of steady progress, exciting meetings and a few key milestones across our projects. We'd love to say the weather has been on our side this week but unfortunately that wasn't the case! On a couple of projects where we needed to expose existing roofs, the heavy rain presented a few challenges. Thankfully, the team adapted where they could and continued making good progress across our projects.
Here’s what we’ve been up to 👇
🔹 Warminster
We've been carrying out second fix plumbing works, bringing the project another step closer to completion.
🔹 Salisbury (Extension)
The steels have now been ordered for our Salisbury extension project.
🔹 Codford (Internal Alterations)
Steels have also been ordered for an internal alteration project in Codford. It's always exciting to see structural works moving forward and projects taking shape.
🔹 Amesbury (Extension)
A big milestone this week with the roof and gable brickwork now completed.
🔹 Woodford Valley
Roofing works are nearly complete and we're looking forward to seeing the finished result very soon.
Away from site, Nathan has spent time meeting with new and existing clients, as well as architects, discussing some exciting projects currently in the pipeline. Mid-week was spent with Clive and the team discussing project progress, upcoming work and ensuring everything remains on track behind the scenes.
Have a fantastic weekend everyone and I'll catch up with you all again next week 🏗️✨