20/06/2026
Chorlton Project update 🏠
The front elevation is almost fully slated - before we could get there though, we had to work through a 25mm deflection across the roof caused by a poorly built loft conversion. To correct it, we packed the base out from 25mm down to 10mm across the bottom half of the roof. Around the back, the chimney's been rebuilt and raised five courses with a fresh flaunch and an extended liner.
Next up, it's the lead work, ridges, and a mortar fillet up the gable - then we move onto the outrigger. On track to finish on time.
More updates to follow!