Progress continues at the Heavitree Theatres project in Exeter.
The latest aerial views capture two key stages of the build. Reinforcement and formwork are progressing across the second floor as further concrete pours continue, while below, the temporary support structure is being removed from the ground floor following successful concrete cube test results. With each section achieving the required strength, the formwork is being struck, and back-propping operations are progressing, with completion scheduled for mid-September.
Elsewhere, preparations continue for the next phase, including piling within the courtyard along with the commencement of the new electrical infrastructure, which is due in early September.