PROGRESS UPDATE - London
Heading into the final stretch of this project we are now left with a few items to complete before we hand this site back to the Client.
The concrete yard is around 75% complete which will then just leave the tarmac car park for the external surfacing works.
Fencing & gates will be installed to facilitate controlled access around the site along with the EV chargers and building protection measures.
In Building 2 we await delivery of the landing doors for the lift shaft and the staircase which is ready for installation in due course.
| | |