Coffey

Coffey Coffey is a family-owned engineering company delivering water, energy, transport and civil infrastructure since 1974.

We enhance communities through engineering excellence, working with integrity, innovation and teamwork across Ireland and the UK. Coffey is a family-owned business with a significant presence across the Water, Transport, Energy and Civil Engineering Industries throughout Ireland and the UK. We have proud history in delivering projects on time, safely and within budget for our clients in Ireland since 1974 and in the UK since 1988.

๐ƒ๐ž๐ฅ๐ ๐š๐ง๐ฒ ๐ญ๐จ ๐๐ฅ๐š๐œ๐ค๐ฅ๐ข๐จ๐ง ๐‚๐ก๐š๐ฉ๐ž๐ฅ ๐‘๐จ๐š๐ ๐ˆ๐ฆ๐ฉ๐ซ๐จ๐ฏ๐ž๐ฆ๐ž๐ง๐ญ ๐’๐œ๐ก๐ž๐ฆ๐ž | ๐’๐ž๐œ๐ญ๐ข๐จ๐ง 2 ๐๐ซ๐จ๐ ๐ซ๐ž๐ฌ๐ฌ  Coffey is continuing work on the ๐ƒ๐ž๐ฅ๐ ๐š๐ง๐ฒ ๐ญ๐จ ๐๐ฅ...
02/09/2026

๐ƒ๐ž๐ฅ๐ ๐š๐ง๐ฒ ๐ญ๐จ ๐๐ฅ๐š๐œ๐ค๐ฅ๐ข๐จ๐ง ๐‚๐ก๐š๐ฉ๐ž๐ฅ ๐‘๐จ๐š๐ ๐ˆ๐ฆ๐ฉ๐ซ๐จ๐ฏ๐ž๐ฆ๐ž๐ง๐ญ ๐’๐œ๐ก๐ž๐ฆ๐ž | ๐’๐ž๐œ๐ญ๐ข๐จ๐ง 2 ๐๐ซ๐จ๐ ๐ซ๐ž๐ฌ๐ฌ

Coffey is continuing work on the ๐ƒ๐ž๐ฅ๐ ๐š๐ง๐ฒ ๐ญ๐จ ๐๐ฅ๐š๐œ๐ค๐ฅ๐ข๐จ๐ง ๐‚๐ก๐š๐ฉ๐ž๐ฅ ๐‘๐จ๐š๐ ๐ˆ๐ฆ๐ฉ๐ซ๐จ๐ฏ๐ž๐ฆ๐ž๐ง๐ญ ๐’๐œ๐ก๐ž๐ฆ๐ž, delivering upgrades to road, pedestrian, cycling and utility infrastructure along the route.

The scheme is designed to improve connectivity between Delgany and Blacklion, with works including new and upgraded pedestrian and cycling facilities, drainage and utility infrastructure, road improvements, public lighting and associated accommodation works.

๐’๐ž๐œ๐ญ๐ข๐จ๐ง 2 ๐๐ซ๐จ๐ ๐ซ๐ž๐ฌ๐ฌ
Work on Section 2 has continued to move forward, with recent activity focused on road construction, drainage, kerbing and pedestrian infrastructure.

Since our previous update, works have included:

โœ”๏ธ Earthworks completed across an area of 770mยฒ
โœ”๏ธ 2,300mยฒ of base and binder course surfacing completed
โœ”๏ธ 430m of slipform kerbing installed, bringing the total to 650m
โœ”๏ธ 150m of precast driveway and bus kerbs installed
โœ”๏ธ 1,020mยฒ of footpaths installed
โœ”๏ธ A further 950mยฒ of cycle track installed
โœ”๏ธ Mainline deep drainage works completed

This latest progress builds on the utility and accommodation works previously completed in Section 2, as the road, footpath and associated infrastructure continues to take shape along the route.

The improvements being delivered will provide safer and more accessible infrastructure for pedestrians, cyclists and road users, while improving connectivity between Delgany and Blacklion.

Find out more about Coffeyโ€™s work across transport infrastructure:
www.coffeygroup.com

๐€ ๐ง๐ž๐ฐ ๐œ๐ก๐š๐ฉ๐ญ๐ž๐ซ ๐Ÿ๐จ๐ซ ๐‚๐ก๐ฎ๐ซ๐œ๐ก ๐’๐ญ๐ซ๐ž๐ž๐ญ ๐ข๐ง ๐‘๐จ๐ฌ๐œ๐จ๐ฆ๐ฆ๐จ๐ง.For years, Church Street has been a key part of daily life in Roscommon, a ...
01/09/2026

๐€ ๐ง๐ž๐ฐ ๐œ๐ก๐š๐ฉ๐ญ๐ž๐ซ ๐Ÿ๐จ๐ซ ๐‚๐ก๐ฎ๐ซ๐œ๐ก ๐’๐ญ๐ซ๐ž๐ž๐ญ ๐ข๐ง ๐‘๐จ๐ฌ๐œ๐จ๐ฆ๐ฆ๐จ๐ง.

For years, Church Street has been a key part of daily life in Roscommon, a place where people shop, meet, work and pass through every day.

Today, that familiar street has been reimagined as a safer, more accessible and more welcoming public space, creating a better experience for residents, businesses and visitors alike.

The completed transformation, recently featured in the Roscommon People, is another example of how investment in public infrastructure can support the long-term regeneration of our town centres. Small changes to the built environment can have a significant impact on how people move through, connect with and experience a place.

Working alongside Roscommon County Council, Coffey delivered this project with a shared focus on creating lasting value for the community and supporting a vibrant future for Roscommon.

Projects like Church Street bring our purpose, Enhance Communities through Engineering Excellence, to life. Not just through the infrastructure itself, but through the positive difference it makes to everyday life.

A big thank you to everyone involved in bringing this transformation from concept to completion.

๐€ ๐†๐ซ๐จ๐ฐ๐ข๐ง๐  ๐๐ฎ๐ฌ๐ข๐ง๐ž๐ฌ๐ฌ ๐๐ž๐ž๐๐ฌ ๐š ๐‚๐จ๐ง๐ง๐ž๐œ๐ญ๐ž๐ ๐“๐ž๐š๐ฆ  As Coffey grows, creating opportunities for our people to build relationships...
01/09/2026

๐€ ๐†๐ซ๐จ๐ฐ๐ข๐ง๐  ๐๐ฎ๐ฌ๐ข๐ง๐ž๐ฌ๐ฌ ๐๐ž๐ž๐๐ฌ ๐š ๐‚๐จ๐ง๐ง๐ž๐œ๐ญ๐ž๐ ๐“๐ž๐š๐ฆ

As Coffey grows, creating opportunities for our people to build relationships across the business matters.

Thatโ€™s why the first outing of the Coffey Golf Society at ATHENRY GOLF CLUB last Friday was about more than getting a round of golf in.

It brought colleagues from different parts of Coffey together away from projects, sites and offices, giving people the chance to get to know one another and strengthen relationships across the business.

And those relationships have value well beyond the day itself.

The better connected we are internally, the easier it is to share knowledge, bring different expertise together and collaborate across teams. Ultimately, that helps us bring more of Coffeyโ€™s collective capability to the challenges our clients ask us to solve.

For us, thatโ€™s Do It Together in practice: stronger connections between our people, better collaboration across our business and better outcomes for our clients.

A big thank you to everyone who took part and helped get the Coffey Golf Society off to a great start. Weโ€™re looking forward to seeing it grow and bringing even more colleagues together in the outings ahead.

๐Ž๐ฎ๐ซ ๐๐ข๐ ๐ ๐ž๐ฌ๐ญ ๐‹๐ข๐ง๐ž-๐”๐ฉ ๐˜๐ž๐ญ: ๐‚๐š๐ซ๐ž๐ž๐ซ ๐Ž๐ฉ๐ฉ๐จ๐ซ๐ญ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐€๐œ๐ซ๐จ๐ฌ๐ฌ ๐ˆ๐ซ๐ž๐ฅ๐š๐ง๐ & ๐ญ๐ก๐ž ๐”๐ŠIf Electric Picnic isn't quite your thing, we've go...
28/08/2026

๐Ž๐ฎ๐ซ ๐๐ข๐ ๐ ๐ž๐ฌ๐ญ ๐‹๐ข๐ง๐ž-๐”๐ฉ ๐˜๐ž๐ญ: ๐‚๐š๐ซ๐ž๐ž๐ซ ๐Ž๐ฉ๐ฉ๐จ๐ซ๐ญ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐€๐œ๐ซ๐จ๐ฌ๐ฌ ๐ˆ๐ซ๐ž๐ฅ๐š๐ง๐ & ๐ญ๐ก๐ž ๐”๐Š

If Electric Picnic isn't quite your thing, we've got another kind of line-up.

We're hiring across Ireland and the UK for roles including:
โ€ข Engineers
โ€ข Quantity Surveyors
โ€ข HSQE Professionals
โ€ข Project & Construction Specialists

While thousands head to the fields this weekend, our teams are busy delivering the infrastructure that keeps communities connected, from water and energy projects to transport and civil engineering works.

At Coffey, you'll be part of a business that's been engineering critical infrastructure for over 50 years, working alongside talented people who are committed to doing great work, supporting one another, and continually improving.

Our values shape how we work every day:
Do the Right Thing
We act with integrity and earn trust through every decision.
Do it Better
We constantly improve by learning, sharing, and striving for excellence
Do it Together
We succeed through teamwork, collaboration, and shared purpose.

Why join Coffey?
โ€ข Family-owned, engineering-led business with a strong track record across Ireland and the UK.
โ€ข Opportunities to work on projects that make a tangible difference to communities.
โ€ข A supportive culture focused on development, learning, and long-term careers.
โ€ข The chance to help deliver the infrastructure of tomorrow.
No camping required. Wellies optional.

Explore our current opportunities: https://careers.coffeygroup.com

๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ ๐€๐ฎ๐ ๐ฎ๐ฌ๐ญ ๐๐ž๐ฐ๐ฌ๐ฅ๐ž๐ญ๐ญ๐ž๐ซAugust has been a month of progress, innovation and community connection at Coffey.In our latest...
27/08/2026

๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ ๐€๐ฎ๐ ๐ฎ๐ฌ๐ญ ๐๐ž๐ฐ๐ฌ๐ฅ๐ž๐ญ๐ญ๐ž๐ซ

August has been a month of progress, innovation and community connection at Coffey.

In our latest newsletter, we highlight key project updates, community initiatives and announcements from across the business, showcasing how our teams are delivering essential infrastructure and creating lasting value for the communities we serve.

Read the latest Coffey newsletter here: https://www.linkedin.com/pulse/welcome-coffey-august-2026-newsletter-coffey-group-oey1f

August has been a month of progress, collaboration and responsible delivery at Coffey. From advancing critical water infrastructure projects to sharing knowledge with Severn Trent and progressing our sustainability commitments, our teams continue to support better outcomes for communities and the en

๐Œ๐š๐ฒ๐Ÿ๐ข๐ž๐ฅ๐ ๐’๐“๐– ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญ ๐”๐ฉ๐๐š๐ญ๐ž Significant progress continues at Mayfield STW for Severn Trent Water, with several key mile...
26/08/2026

๐Œ๐š๐ฒ๐Ÿ๐ข๐ž๐ฅ๐ ๐’๐“๐– ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญ ๐”๐ฉ๐๐š๐ญ๐ž

Significant progress continues at Mayfield STW for Severn Trent Water, with several key milestones achieved across the site in recent weeks. The project includes upgrades to increase treatment performance and flow capacity, including a new biofilter recirculation pumping station, EICA improvements and a new MCC installation.

โ€ข Installation of the new recirculation pumping station is now complete.
โ€ข Sitewide ducting installation has been completed.
โ€ข The new MCC has been delivered and first-fix installation works are complete.
โ€ข The temporary SAF unit has been successfully relocated to facilitate construction of the new storm tank.
โ€ข The storm tank base has been installed and is ready to receive the tank in early September.
โ€ข Electrical installation works continue across the site.

Over the coming weeks, the team will focus on final installations and commissioning activities, with the new treatment assets expected to be fully operational by the end of the month.

The scope of the project has grown significantly since construction commenced. In addition to the original upgrade works, Coffey has been engaged to deliver the relocation of the temporary SAF unit, installation of a new storm tank, provision of a washwater booster system and, most recently, a standby generator installation.

The SAF relocation and storm tank elements are expected to be completed by the end of the month, while the washwater booster system and backup generator works will continue into next year, with overall project completion now anticipated in early 2027.

A great example of collaborative delivery as the team continues to enhance wastewater infrastructure and operational resilience for Severn Trent Water.

Please contact [email protected] if you wish to learn more about this project and how Coffey is delivering critical water infrastructure projects for our clients.

๐’๐ญ๐ซ๐จ๐ง๐  ๐œ๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐š๐ซ๐ž ๐›๐ฎ๐ข๐ฅ๐ญ ๐ฐ๐ก๐ž๐ง ๐ฉ๐ž๐จ๐ฉ๐ฅ๐ž ๐œ๐จ๐ฆ๐ž ๐ญ๐จ๐ ๐ž๐ญ๐ก๐ž๐ซ. On 11-12 September, St. Mary's GAA Club Athenry will bring the l...
25/08/2026

๐’๐ญ๐ซ๐จ๐ง๐  ๐œ๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐š๐ซ๐ž ๐›๐ฎ๐ข๐ฅ๐ญ ๐ฐ๐ก๐ž๐ง ๐ฉ๐ž๐จ๐ฉ๐ฅ๐ž ๐œ๐จ๐ฆ๐ž ๐ญ๐จ๐ ๐ž๐ญ๐ก๐ž๐ซ.

On 11-12 September, St. Mary's GAA Club Athenry will bring the local community together for its Family Fun Day and 24-Hour Walkathon, while also marking the official opening of its new Astro Pitch and Wall Ball facility.

Weโ€™re delighted to support this yearโ€™s event as a main sponsor, with Coffey contributing โ‚ฌ1,000 towards the fundraiser to help support the club and the continued development of facilities for the wider community.

With strong roots in Athenry and many connections to St Maryโ€™s across our workforce, this support means a great deal to our people.

St Maryโ€™s has grown to become much more than a sports club. Through GAA for All, its work with local schools and community groups, and the development of accessible recreational facilities, the club is creating opportunities for people of all ages and abilities to participate, connect and stay active.

Itโ€™s a great example of values we share at Coffey: Do the Right Thing, Do it Better and Do it Together. Supporting communities, creating opportunities and working together can make a lasting difference.

We wish the volunteers, families, club members and everyone involved every success with the Family Fun Day, Walkathon and the official opening of these new facilities.

๐’๐ก๐š๐ซ๐ข๐ง๐  ๐Š๐ง๐จ๐ฐ๐ฅ๐ž๐๐ ๐ž ๐ญ๐จ ๐ˆ๐ฆ๐ฉ๐ซ๐จ๐ฏ๐ž ๐–๐š๐ญ๐ž๐ซ ๐ˆ๐ง๐Ÿ๐ซ๐š๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐ž ๐ƒ๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒLast week, Paul Baxter and Anne Carroll from Severn Trent join...
24/08/2026

๐’๐ก๐š๐ซ๐ข๐ง๐  ๐Š๐ง๐จ๐ฐ๐ฅ๐ž๐๐ ๐ž ๐ญ๐จ ๐ˆ๐ฆ๐ฉ๐ซ๐จ๐ฏ๐ž ๐–๐š๐ญ๐ž๐ซ ๐ˆ๐ง๐Ÿ๐ซ๐š๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐ž ๐ƒ๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ

Last week, Paul Baxter and Anne Carroll from Severn Trent joined us in Ireland for a two-day visit focused on sharing knowledge, exchanging ideas and seeing projects in delivery first-hand.

The visit included our Athenry office, the Coftec assembly facility and three water infrastructure project sites delivered for another client: Enfield WTP, Castletroy WwTP and Lough Talt.

Visiting projects in person gives a practical view of how engineering solutions perform in real operating environments. It also creates an opportunity for open discussion about the challenges facing the water industry and how we can respond to them.

Paul and Anne met with members of the Coffey and Coftec teams, toured our modular assembly facility and discussed approaches to delivering water infrastructure more efficiently, while maintaining quality, performance and value.

A key part of the discussion was the role of standardisation, reduced reliance on site civils and value-driven design. Designing with repeatability and practical delivery in mind can help simplify construction and improve efficiency without compromising performance.

Across the two days, both teams shared experience, asked questions and discussed lessons from projects at different stages of delivery. This approach reflects our focus on learning, sharing knowledge and working together to improve how infrastructure is delivered.

Thank you to Paul and Anne for spending the time with our teams and visiting our project sites. We value our collaboration with Severn Trent and the opportunity to keep sharing ideas around the delivery of critical water infrastructure.

๐„๐ฑ๐œ๐ข๐ญ๐ข๐ง๐  ๐‚๐š๐ซ๐ž๐ž๐ซ ๐Ž๐ฉ๐ฉ๐จ๐ซ๐ญ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐š๐ญ ๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ!Looking for a career where you can make a real and lasting impact?At Coffey, we'...
21/08/2026

๐„๐ฑ๐œ๐ข๐ญ๐ข๐ง๐  ๐‚๐š๐ซ๐ž๐ž๐ซ ๐Ž๐ฉ๐ฉ๐จ๐ซ๐ญ๐ฎ๐ง๐ข๐ญ๐ข๐ž๐ฌ ๐š๐ญ ๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ!

Looking for a career where you can make a real and lasting impact?

At Coffey, we're delivering the critical infrastructure that supports communities across Ireland and the UK. From water and energy to transport and civil engineering, our projects help improve everyday lives while contributing to a more sustainable future.

As our business continues to grow, we're looking for talented and motivated people who want to grow with us and be part of something meaningful.

Our values guide everything we do:
๐ƒ๐จ ๐ญ๐ก๐ž ๐‘๐ข๐ ๐ก๐ญ ๐“๐ก๐ข๐ง๐  We act with integrity, take responsibility, and build trust through our actions.
๐ƒ๐จ ๐ข๐ญ ๐๐ž๐ญ๐ญ๐ž๐ซ We challenge ourselves to learn, improve, and deliver excellence every day.
๐ƒ๐จ ๐ข๐ญ ๐“๐จ๐ ๐ž๐ญ๐ก๐ž๐ซ We achieve more through collaboration, teamwork, and a shared commitment to success.

Why Choose Coffey?
โ€ข A family-owned, engineering-led business with over 50 years of industry experience.
โ€ข A team committed to quality, safety, and engineering excellence.
โ€ข A supportive and collaborative culture where people are empowered to develop and succeed.
โ€ข The opportunity to build a rewarding long-term career while working on projects that make a tangible difference.

Whether you're starting your career journey or looking for your next challenge, you'll join a team that's delivering tomorrow's infrastructure and enhancing communities through engineering excellence.

Interested in joining Coffey? We'd love to hear from you.

Apply now: https://lnkd.in/e-4Sqvi2

๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ'๐ฌ ๐’๐๐“๐ข ๐•๐š๐ฅ๐ข๐๐š๐ญ๐ž๐ ๐“๐š๐ซ๐ ๐ž๐ญ๐ฌ ๐€๐ซ๐ž ๐๐จ๐ฐ ๐‹๐ข๐ฏ๐žFollowing the validation of our near-term science-based emissions reduction ...
20/08/2026

๐‚๐จ๐Ÿ๐Ÿ๐ž๐ฒ'๐ฌ ๐’๐๐“๐ข ๐•๐š๐ฅ๐ข๐๐š๐ญ๐ž๐ ๐“๐š๐ซ๐ ๐ž๐ญ๐ฌ ๐€๐ซ๐ž ๐๐จ๐ฐ ๐‹๐ข๐ฏ๐ž

Following the validation of our near-term science-based emissions reduction target by the Science Based Targets initiative (SBTi), our targets are now publicly available.

Publishing our targets is an important step in turning commitment into action. It provides a clear roadmap for reducing emissions across our operations and supply chain, while creating measurable accountability for our progress.

As an infrastructure business, we recognise the role we play in supporting the transition to a lower-carbon future. Science-based targets give us a framework to drive meaningful emissions reductions and help meet the evolving sustainability expectations of our customers, partners and stakeholders.

The next phase of this journey is focused on delivery. Through innovation, collaboration and continuous improvement, we are working to reduce our environmental impact while continuing to deliver essential infrastructure across Ireland and the UK.

You can view our SBTi approved targets here: https://sciencebasedtargets.org/target-dashboard

Address

Moanbaun
Athenry

Opening Hours

Monday 9am - 5pm
Tuesday 9am - 5pm
Wednesday 9am - 5pm
Thursday 9am - 5pm
Friday 9am - 5pm

Telephone

+35391844356

Alerts

Be the first to know and let us send you an email when Coffey posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Coffey:

Shortcuts

Share