🏗️ Project Update: Sahaj Broadway
Steady progress and strong ex*****on continue at Sahaj Broadway!
✅ Raft Work – 95% Complete
✅ Footing Work – 90% Complete
For the 1,850 sqm Raft area, the project has achieved a total material consumption of:
🔹 226 MT of Steel
🔹 2,163.5 Cum of Concrete
Concrete Consumption Breakdown:
▪️ M15 – 236 Cum
▪️ M25 – 1,860 Cum
▪️ M35 – 67 Cum
Looking ahead, our dedicated site team is actively preparing for the casting of the 1,675 sqm slab.
Every milestone reflects our commitment to quality, precision, and timely ex*****on. A big appreciation to everyone involved for their dedication, coordination, and continuous efforts in driving the project forward.