08/05/2026
Project Update: Ongoing Road Works
Construction works are currently in progress on the Got Nanga – Jera – Bar Ber Road, with ongoing activities on the TSG Layer section.
Current activities include:
• Full dumping of base material between Km 5+760 – Km 5+820
• Full dumping of base material between Km 5+980 – Km 6+060