The AKSEM project in Padang Besar challenged us to rethink how housing could be delivered faster, better, and more efficiently in a remote location.
Working closely with JKR, we explored a range of construction methods, including large-scale 3D concrete printing using technology supplied by COBOD. Several units within the 125-unit development were identified as pilot projects. if successful they were supposed to be implemented in all other jkr projects .While the technology showed promise, the quality of the printed finish did not achieve the standards required for the project.
Innovation, however, is not about adopting the newest technology. It is about selecting the most appropriate solution.
We ultimately adopted a load-bearing masonry concrete block system based on IBS principles. The system eliminated the need for conventional columns and beams in much of the development, reducing construction sequences and accelerating progress on site.
Every block, reinforcement bar, lintel, stiffener services, conduit and ducting had to be carefully planned in advance. Concrete was poured into selected cavities within the blocks, creating an integrated structural system that was both efficient and robust. The blocks also offered lower porosity than traditional bricks, reducing the risk of water pe*******on and mould growth.
For us, this project reinforces a simple principle: every project deserves its own solution. The most successful outcome is rarely determined by the newest technology, but by the careful evaluation of available options and the disciplined selection of what works best for the client, the site and the long-term performance of the building.