03/08/2026
132kV Power Transformer & 33kV Earthing Transformer Factory Acceptance Test (FAT) Successfully Completed for our Renewable Interconnection Facilities Projects at Gurun, Kedah.
At Kee Ming Group, quality is not merely a requirement, it is the foundation of every project we deliver.
Our engineering team has successfully completed the Factory Acceptance Test (FAT) for the Power Transformer and Earthing Transformer at the manufacturerโs production facility in Shanghai, China, for the Earthing Transformer and Changzhou, China, for the Power Transformer, marking another significant milestone for the Corporate Green Power Programme (CGPP), Solar Project located in Gurun, Kedah.
Delivered in close collaboration with our clients, this FAT ensures that all transformer equipment fully complies with the projectโs technical specifications, client requirements, and internationally recognised IEC standards before shipment to the site.
The witnessed FAT programme comprised comprehensive inspections and testing, including:
โ๏ธ Visual and dimensional inspection
โ๏ธ Verification of transformer ratings, vector group, and nameplate data
โ๏ธ Winding resistance measurement
โ๏ธ Transformer Turns Ratio (TTR) testing
โ๏ธ Insulation resistance measurement
โ๏ธ Applied voltage and induced voltage withstand tests
โ๏ธ Temperature Rise Test to verify the transformerโs thermal performance under rated loading conditions
โ๏ธ Functional verification of cooling system, protection devices, and accessories
โ๏ธ Oil quality verification and sealing integrity checks
โ๏ธ Review of certified test reports, factory quality documentation, and manufacturing records
Every inspection and test was conducted to verify the highest levels of performance, reliability, safety, and long-term operational integrity, ensuring the equipment is fully prepared for installation and energisation.
As the appointed engineering and construction partner, Kee Ming Group remains committed to delivering critical power infrastructure through stringent quality assurance, technical excellence, and adherence to international engineering best practices.
We extend our appreciation to our client, the manufacturer Sieyuan Electric Co Ltd, consultants, and all project stakeholders for their professionalism, collaboration, and commitment throughout the FAT process.
Together, we continue to build reliable and sustainable energy infrastructure for Malaysiaโs renewable energy future.