13/08/2026
Someone quoted ₦17.5 million. My preliminary estimate was about ₦22 million. So, who was right?
A few days ago, i was given the architectural drawings for a proposed standard 4 bedroom bungalow to estimate materials from foundation, concrete fascia (parapet) to entire roofing phase together with the workmanship labour cost.
Like every construction project, the first question was simple:
How much will it take?
But for me, answering that question wasn't about looking at the building and throwing a figure into the air.
I went into the drawings.
I studied the dimensions.
The foundation layout.
The walling.
The reinforcement requirements.
The roofing configuration.
The timber requirements.
The blocks.
Cement.
Sand.
Gravel.
Laterite.
And the other materials that would eventually turn those lines on paper into an actual building.
From that assessment, i prepared a preliminary material quantity estimate.
The figure for materials came to roughly ₦22 million while workmanship labour cost was ₦3.5million... which was a total of ₦25.5million for the agreed phases of work.
But i made something very clear:
This was an estimate. It was not a BOQ or final quotation.
It was simply a working figure to give the client an idea of what the material requirement could look like based on the drawings and the standard specifications i was considering.
Then came the interesting part.
I was told that someone else had already given the client a figure of about ₦17.5 million.
₦15 million for materials.
₦2.5 million for workmanship.
And honestly, that immediately made me pause.
Not because i believed the other person was wrong.
But because i know construction.
The same drawing can produce very different figures depending on what is actually being priced.
So the question shouldn't immediately be:
Why is yours more expensive?
The better question is:
What exactly is included in each figure?
What quantity of reinforcement is being allowed?
What sizes of reinforcement?
What specification and gauge of roofing sheets?
How much timber is being provided?
What sizes of timber?
How many blocks?
What cement quantity?
How much sand and granite?
How much laterite is required for filling and backfilling?
What about transportation?
What about wastage?
What about the small but important construction materials that are often forgotten during preliminary estimation?
And most importantly...
Are both figures based on the same standard and the same scope of work?
Because if they are not, then comparing ₦17.5 million to ₦25.5 million simply because they are both figures for the same building doesn't really tell us much.
And that's one lesson i continue to learn in this industry:
The cheapest quotation is not always the cheapest construction.
Sometimes, the difference isn't that someone is trying to charge more.
Sometimes, the difference is hidden inside the quantity, specification and quality of what has been allowed for.
This is why i have become increasingly interested in the part of construction that happens before construction actually begins.
The measurements.
The drawings.
The quantities.
The specifications.
The estimates.
The questions.
Because when these things are properly understood from the beginning, the client can make an informed decision instead of simply choosing the lowest figure on the table.
And that's the kind of relationship i want to build through UNVA DESIGN & CONSTRUCTION COMPANY LIMITED.
Not just giving you a price.
Not just telling you what you want to hear.
But sitting with the drawings, studying the project, understanding what it will take, and helping you make a construction decision you can defend.
Because at the end of the day, we are not competing to produce the cheapest number.
We are working towards producing the right building, with the right specification, for the right investment.
So if you have your architectural drawings already and you're wondering:
How much will this building actually require?
Don't guess.
Don't rely solely on a verbal estimate.
Let the drawings speak.
Send your drawings to UNVA DESIGN & CONSTRUCTION COMPANY LIMITED, and let's assess the project properly... from quantities and specifications to a realistic construction plan.
From concept, to quantities, to construction.