18/05/2026
DAY 44 — 49 — PHASE 5 PROGRESS UPDATE
The structure is rising steadily.
We are currently in Phase 5 — progressing from the reinforced concrete slab level up to the parapet stage, and over the past few days, major structural activities have been ongoing on site.
From:
✔ Pillar formwork and casting
✔ Lintel reinforcement works
✔ Column casting
✔ Blockwork progression
…we are now wrapping up towards the parapet level.
At this stage, every detail matters.
Internally, we maintained 3 block courses, while externally we introduced 2 courses, making provision for the concrete fascia/parapet structure to follow.
This is how coordinated construction should look:
Every phase connected. Every team aligned. Every process intentional.
At Techno Engineering & Construction Ltd, we don’t just build fast —
we build with structure, engineering precision, and long-term durability in mind.
And yes, we are still fully on track toward completing this project within the 90-day timeline.