A big week of progress on our project at Silverdale, including one very early start!
At midnight on Friday, the team kicked off one of the largest pours on the project to date: 1,100m² of internal floor slab.
Over the next six and a half hours, 180m³ of concrete arrived across 45 truckloads, with the full slab in place by 6.30am.
It followed another early morning pour earlier in the week for the suspended car park slab, while overhead the roof is now complete and the building is increasingly taking shape.
These are the milestones that change a project quickly. A huge amount of planning, coordination and work goes into a few hours on site, and by sunrise the building looked very different from the night before.
Great work from everyone involved in keeping Silverdale moving.