As we move forward with our restoration efforts, our team remains fully committed to ensuring safe, reliable, and efficient electrical service for every home and establishment affected
Part 2 _ ACCOMPLISHMENT REPORT
November 18, 2025
📍Hda. Paghidait, Brgy Luna
📍Hda. Doming, Brgy Luna
Removal and Install Primary Poke Hang-up 15 kVa Transformer.
Restore Wiredown Secondary 2 Span
November 19, 2025
📍Dongcolan, Cadiz Viejo
Removal and Install 2 Secondary Pole
November 20, 2025
📍Caridad 3, Brgy. Luna
📍Hda. Pay him, Brgy Burgos
Removal and Install Secondary Pole
Removal and Install 1 Primary Pole 40 ft
Removal and Install 2 Secondary Pole and Metering 30 ft
November 21, 2025
📍Maloga/ San Juan, Brgy. Burgos
Removal and Install Primary Line
Replace Pole Tap-in
Restore Wiredown Primary 3 Spanning
November 22, 2025
📍Hda. Letecia, Brgy Caduhaan
📍Hda. Edad, Brgy Caduhaan
Removal and Install 3 Primary Pole
November 23, 2025
📍San Jose, Brgy Andres Bonifacio
Removal and Install 1 Primary Pole and Hang-up 15 kVa Transformer
November 24, 2025
📍Hda. San Jose, Hda. Madayo
📍Hda Tresing Brgy Andres Bonifacio
📍Marianas, Brgy. Caduhaan
Removal and Install 1 Primary Pole and Hang-up 15 kVa Transformer
Restore and Wiredown 2 Span Secondary Pole
November 25, 2025
📍Purok Mapainubuson, Brgy. Burgos
Sitio. Bagroy, Brgy. Burgos
Removal and Install 1 Secondary Pole
Removal and Install 1 Primary Pole
November 26, 2025
📍Hda. Felomina, Brgy. Burgos
Removal and Install 1 Primary Pole, 1 Secondary Pole and Metering
November 27, 2025
📍Babira, Sagay City
Repair Cut-off Secondary 2 Span
November 28, 2025
📍Consing, Sagay City
Restore Wiredown 8 Span
November 29, 2025
📍Siwahon 1, Sagay City
Re-sag Primary and Secondary Line
December 2, 2025
📍Hda. Felomina, Brgy. Burgos
Removal, Install 15 kVa, and Hang-up 15kVa Transformer
December 3, 2025
📍Sitio. Alingating, Brgy. Tinampaan
Removal and Install 2 Primary Pole
Hang-up Transformer 15 kVa and Clearing
Repair Cut-off Secondary Line
December 4, 2025
📍Cadiz Heights
Removal, Install 37.5 kVa and Hang-up 50 kVa
December 5, 2025
📍Hda. Pag-asa, Brgy Luna
Removal, Install Primary Line and Transformer
December 6, 2025
📍Cadiz Heights
📍Purok, Dungcaan
Removal and Install 2 Secondary Pole
Removal and Install Primary Pole 3 Phase Single Pole