Simple three bedroomed house                       Accountability simple three bedroomed house ( plot size  50by50) from...
26/06/2026

Simple three bedroomed house

Accountability simple three bedroomed house ( plot size 50by50) from foundation up the wallplate.
OWNER MR
Material required
1.blocks @ 6,000 trips costs 260,000 each trip consists of 1000bricks×8trips #1,560,000
2.hollow blocks @ 2500 each block costs 19,00 #4,750,000
3.omusenyu
Lake sand @ 3trips of forward box55000 #1,650,000
Plaster sand of forward box ×550,000 #1,100,000
4.cement @ 80bags ×34500 #2,760,000
5.iron bars
Y12 @ 25pieces ×45,000 #1.125,500
Y10@ 15pieces ×25,000 #375,000
6.baing wires ×150,000 #150,000
7.ring wires (r7) ×15,000 #375,000
8.kilundu ×8,000 #320,000
9.bottoms @ 15pieces ×6,000 #90,000
10.nails
Inch4 =10kgs×5500 #55,000
3= 10kgs×5500 #55,000
5=10kgs×5500 #55,000
2⅓=5kgs ×6500 #32500
11.dpc ×3000 #45,000
12.sisal ×7,000 #28,000
13.soft stones @1 trips of forward flat #250,000
14.hoop alron @ 5roles×45,000 #225,000
15.plain sheets ×15,000 #144,000
16.transport costs #300,000
11.micelinious costs #1,200,000

Total amount = 16,645,000
Labour required = ........................

Note this
Tools needed at the site will be un offer from the company

THANKS ALOT FOR THE OPPORTUNITY

kk trust builders group Uganda                       Limited        check out this opportunity you can definitely fix su...
19/06/2026

kk trust builders group Uganda
Limited
check out this opportunity you can definitely fix such Aproject in a 100by 50
6units
it's accountability is available and it's consultation is free of charge
grab it accountability through our WhatsApp number

0708282239
Asalam alaikum walahumatulahi wabalakatuh

FROM KK TRUST BUILDERS GROUP UGANDA                      LIMITED.       Accountability ( ( first phase)          Mpambil...
04/06/2026

FROM KK TRUST BUILDERS GROUP UGANDA
LIMITED.
Accountability ( ( first phase)


Mpambile project
Owner ...........................

3BEDROOMED HOUSE FROM FOUNDATION UP TO THE WALLPLATE
MATERIAL REQUIRED

1.BLOCKS @ 220,000 ( normal blocks) each trip costs 260,000×22trips #5,720,000
2.cement @ 120bags×33,000 #3,960,000
3.omusenyu
Lake sand of snaltruck #(yellow sand ) #1,800,000
Plaster sand of snaltruck #1,700,000
4. Soft stones @ 1trip of forward flat #250,000
5.iron bars
T12 ×42,000 #1 470,000
T10@15pieaces×25,000 #375,000
6.ring wires @(r7) 20peaces ×13,000 #260,000
7.bainig wires@1role #150,000
8.kilundu ×8,000 #480,000
9.bottoms @ 15pieces ×6,000 #90,000
10.nails
Inch4 =10kgs×55,000 #55,000
3=10kgs×5500 #55,000
1½=5kgs×6500 #32500
11.hoop alron ×45,000 #225,000
12.sisal ×7,000 #28,000
12.plain sheets ×70,000 #140,000
13.dpc ×3000 #45,000
13.kalitunsi ×4,000 #160,000
14.transport costs #200,000
11.micelinious costs #1,500,000( watter billies e.t.c)

Total material =18,695,500
Labour required = ...............


negotiable

Thanks for the opportunity 🙏

NOTE THIS
Tools needed at the site will be an offer from the company

Plz don't not forget to look for us through
What's app 0708282239
Call direct on 0773753640

ASALAM ALAIKUM WALAHUMATULAHI WABALAKATUH

Address

Lubugumu Off Entebbe Road
Kampala

Telephone

+256708282239

Website

Alerts

Be the first to know and let us send you an email when Kk trust builders group posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share