06/07/2026
Bathroom progress update:
Laying Tile = 90% ✅
* Monday: Finish floor tile, set bench, tile niche.
* Tuesday: Grout and measure for frameless shower glass
* Wednesday: Light drywall finishing/ prime, install baseboards, quarter round and caulk.
* Thursday: Clean, Paint x1 (AM) and install new plumbing fixtures, Paint x2 (PM)
Friday: Done ✅ (Until I meet the glass installers the following week once fabrication is done)
All together, 23 days, start to finish.